Because the size of Flatwork Ironer with 3 rollers are two big ,it needs to be took off this machine into two pcs that Part A and Part B
1 Flatwork Ironer’s Part A and Part B are supposed to be connected by nuts and screw ,holes are left on the machine in advance ,and those screw and nuts are packed and put into flatwork Ironer ‘s electricity box
When client get this three roller flatwork ironer please fix Part A and Part B by those Nuts and Screw
2 After Part A and Part B are installed ,please install steam pipes by pipes sent along with flatwork Ironer
The above photo shows steam pipes well completed
After installed the ,flatwork Ironer Ironer’s driven system would like the follows
4 by now ,flatwork Ironer of three rollers has been assembled
5 Instal steam to the steam port of flatwork Ironer ,and also instal one piece of steam valve (Manual )
6 Install electricity power LINES “A B C N “ to electricity box of flatwork Till now the installation job of flatwork ironer has been finished